Claims & rate assessment
Upload a subcontractor claim or variation in any document format. Fiorin auto-extracts every line item into a reviewable grid, matches each line to a rate benchmark, and assesses every rate.
| Line | Claimed | Low · Mid · High | Flag | Adjustment |
|---|---|---|---|---|
| 08 Class 2 formwork, soffit L3 | 214.00 | 138 · 161 · 186 | ELEVATED | −18,020.00 |
| 09 N16 reinforcement, supply & fix | 3,180.00 | 2,940 · 3,120 · 3,340 | WITHIN | 0.00 |
| 10 Formwork stripping & cleaning | 41.50 | 28 · 34 · 39 | ELEVATED | −2,550.00 |
| 11 Crane standing time no tip docket | 465.00 | — | HELD | excluded |
| 12 Additional propping, L3 basis of rate cannot be verified | 24,800.00 | — | HELD | excluded |
Rate benchmarking
A catalogue of construction rates with typed attributes, so a rate is compared with like work. Every entry carries low, mid and high bands, and every band carries the number of observations behind it. The assessment policy that turns a band into a dollar figure is deterministic.
Formwork, Class 2 — soffit
Per m². Each band carries its own observation count.
Chat with your budget
Ask a question the way you would ask a colleague and get the number back in seconds, taken straight from your current budget. Pick up any conversation where you left it, and tell us when an answer helped.
The Level 3 formwork budget is $1,284,500 in this period's budget. Most of it sits in the soffit, with the rest split across columns and walls.
That's $42,600 more than four periods ago. The increase came in Period 27, when the additional propping variation was added. Nothing on this line is currently held for review.
Deterministic Forecast
Upload your budget each period and Fiorin keeps a complete history of your project. Look back at any period, see what changed and why, and know that the figures you reported last month are the same figures you can show today.
Four guarantees under every figure.
Reconciles to the cent
Money is checked against the file's own control total, not an approximation of it.
Flags, never guesses
Ambiguity becomes a data-quality flag. Nothing is silently repaired, dropped, or invented.
Your data, untouched
Fiorin only ever utilises your cost data. Your files and figures stay exactly as you sent them.
Hosted where you need it
Your data is hosted in the region that suits your project and data needs.
Turn your construction cost data into answers.
Access your tender and forecast information through one secure AI-powered workspace.
Request accessAccess on request